Most of a good install is decided before the first bucket. A line laid out right, with every crossing found and every turn painted to a fitting, digs once and passes inspection. A line dug off a guess gets dug twice.
Read the plans. Know the stations, every fitting and valve, the depth of cover and where the line enters the building.
Locates. The 811 ticket is current and the marks are still there. Private lines like irrigation, lot lights and power to signs are not marked by 811: ask the owner or GC.
Pothole every crossing before the ditch is dug. Write down how deep it is.
Find the tie-in point and check it matches the plans. Size and material are in the Tie-in lesson.
White-line the ditch from the tie-in to the building.
Paint the turns to the fitting. Use the angle on a square or a digital angle tool so the paint matches a 45, 22½ or 11¼. No deflection, so the ditch has to match the fitting.
Mark each fitting, the valve and the detector check on the line.
Plan the hole. Spoil on one side, 2 ft back from the edge. A box if it is over 5 ft deep. Traffic and access.
Photo the painted layout before you dig.
Your photos
In TJS Field
One photo of the layout, before the first bucket.
Open TJS Field.
Pick the job.
Tap the camera button, 📷 Take a photo, and take the picture.
Tag it Layout.
In the photo
The white line from the tie-in toward the building