Any work we had to do twice: a failed test, a joint redone, grade fixed, pipe dug back up. Log it the same day.
Pictures load when you are online.
Why it matters
Do-overs are hours the job was never planned for. Logged, we can see what keeps causing them and fix it. Not logged, they just make the job look slow.
A do-over is not about blame. It is about not paying for the same work twice.
Your turn
In TJS Field
Next time something gets redone: log it that day.
Check
3 questions · get all 3
All the steps
Do-over. On Today, tap ↩ Do-over.
What it was. Pick what it was and who it counts against.
Hours lost. Put the man-hours it cost (men × hours) and a note on why.
Save. Save it.
Not a do-over: waiting. Waiting on the inspector or GC is not a do-over. At End of Day, tap it under What made it hard, and say how long in the one line.