The last thing done to a pipe is what keeps it working for years. A rock against the pipe, a hole under it or soft backfill on top shows up later as a break, a sunk patch or a call-back.
Clean trench and a straight pipe first. Before anything covers the pipe: no rock, no trash, no standing water, no loose dirt caving off the walls. Sight down the line: every joint straight, no deflection at a bell.
Tracer wire on top of the pipe, taped to it the whole way, and brought up where the plans call for it.
Haunch it. Work the bedding in under both sides of the pipe by hand so there is no hole underneath.
Photo before you cover. The pipe still exposed: clean trench, tracer wire taped on, haunched, joints straight. Tag it Pipe in trench.
Initial backfill. Clean fill over the pipe to the depth on the plans. No rock against the pipe.
Compact in lifts. One layer at a time, compact each one before the next goes in. Don't run the compactor right on top of the pipe.
Detector tape above the pipe, below grade, at the depth on the plans. Photo it before the next lift goes in. Tag it Backfill.
Finish to grade the same way: lift, compact, lift, compact.
Your photos
In TJS Field
Two photos on every run of pipe.
Open TJS Field.
Pick the job.
Tap the camera button, 📷 Take a photo, and take the picture.
Tag it as below.
Photo 1, before any backfill: tag it Pipe in trench
The pipe is still exposed
The trench is clean
The tracer wire is on top of the pipe and taped
The joints are straight
Photo 2, before the lift over the tape: tag it Backfill